May 17, 2005 - A lot has been happening
since the last entry but it is a bit redundant to maintain a running
commentary on the photo page as well as here. Please visit the
Pictures of the Project Work
on our internal server site.
April 7, 2005 - Well, they did not work
around the clock as there is evidently some county noise ordinance that
they had to comply with. However, I wish they could have just to get
this phase of work over sooner. As it was, the highway was
restricted to one lane for a couple of weeks which required flaggers to
work around the clock. During the night, generators and floodlights
bathed the house in light and a low rumble. Very difficult to sleep.
Yesterday afternoon, the lights were packed up,
holes patched up, and the crews left. It was a great night's sleep!
Drainage problems still exist but the onsite ODOT Inspector told me to
refer the issue up the chain of command. I took pictures and emailed
the folks that I have worked with in the past. I am hopeful that
issues are rectified soon.
Pictures and caption information is posted
on the picture page more regularly than this blog.
March 22, 2005 - Learned that this Friday
night, the crew will be working all night paving our side of the road.
The plan is to re-route traffic Saturday morning onto this new roadbed
next to
the
new curb that is being installed today.
Starting Monday (March 28) the contractor will be
working around the clock to install the new drain pipes on Hwy 213 in
front of our house. The estimate is that this 24-hour work phase
will take 3 or 4 days.
March 11, 2005 - Have not made any entries
for the past few days as the work has been focused on the new Molalla
Avenue road and the widening at the south end of the project. The
new southbound lane is paved and this morning they painted the lines.
Additionally, they graded, graveled, and compacted the new tuning radius
onto Liberal Way.
Today they also started skimming the dirt off of
the soon to be roadbed on our side of the highway. Refer to the
pictures I added on
the image page. It really seems like they are way ahead of
schedule. Especially considering that they originally were not
scheduled to begin work until the end of March. This is an amazingly
weird weather year, in the mid-70s today, and a perfect year for this kind
of work to occur.
March 2, 2005 - The utility work is pretty
much done (I think). There is probably hook up work to complete but
all of there heavy equipment is gone.
Today the heavy equipment of the road contractor
moved in and they began the process of digging the new ditch and using the
soil to fill in the old ditch thus creating the basis of the new road bed. More pictures and update
info added on
the image page.
February 11, 2005 - The utility work is
still underway. It seems as if they will never be done and out
of our hair. It is really noisy, messy, visually upsetting, and the
power outages have been disruptive. It has been about five weeks
since they started and it still looks like they (mainly NW Natural Gas)
won't be done for weeks. I hope that they surprise me.
February 4, 2005 - More pictures and update
info added on
the image page.
February 1, 2005 - I have met with the ODOT
project managers, the general contractor (Nutter) that won the project
bid, with the natural gas company (NW Natural) and with the electric
company (PGE). You can see pictures by
clicking here.
NW Natural has been working on pipeline moves for
a few weeks now and from the looks of it, I would guess that they will be
at it for a couple more. PGE has set the new poles for the main
power transmission lines and is working on stringing the lines.
Wednesday, January 11, 2005 - Well the
project is underway. Sometime last week the utility companies began
the initial stages in preparation for relocating power poles and lines,
gas pipes, etc. I received an email from the ODOT project manager
today saying that he just heard that the contractor was planning on
beginning the project at the end of this month instead of the end of
March. Yikes! The plants that I want to rescue and move in the
path of destruction are barely dormant. It is time to get busy!!!
October 22, 2004 - Dad removed all of the
old fence wire from the driveway up to the corner of the field. John
and I pulled all of the fence posts and relocated them inside the new
property boundary. It really makes the chunk of land we lost
obvious. You can see pictures by
clicking here.
Saturday, July 30, 2004 - This is just a
"catch-up" entry. The appraisal seemed unbiased and pretty fair. It
is a done deal. Paperwork is sign, the project design is complete
with all of our compromises and negotiations, and it should go out for bid
in August and scheduled to start in the spring. This will give us
time to relocate some plants and move a field fence.
In a nutshell, the original design from a decade
ago would have cost us a couple of acres and forced us to relocate out
house on the property. It would have also caused the loss of several
very old trees. The final design required a little over a half acre
and if all goes well, the trees will be spared by using curbs, culverts
and guard rails instead of huge, wide, open ditches. This design
also required less land.
We hope to be able to afford the cost of erecting
a concrete wall along the property line separating the highway from our
front yard. Along with the physical barrier, we are hopeful that it
will deflect some of the noise.
If I was asked to make a recommendation to anyone
dealing with a road project like this, I would highly suggest that you get
to know everyone involved. Keeping an open mind is also helpful.
Realize that a public project will generally occur whether you want it too
or not. Establishing personal relationships with the folks that plan
the project, design it, determine your compensation, etc., is highly
beneficial. They are people too and understand that their
decisions not only benefit all of the citizenry in the area, but impact
your life as well. They have a job to do and from every one I met,
they felt a sense of responsibility to their employers - the citizens of
Oregon.
Monday, April 12, 2004 -
A property appraiser, hired by ODOT, was out today to begin working on
setting a value on the land, fences, and landscaping that they will be
removing.
Coincidentally, commencement of the demolition of
the two houses on the corner of Liberal Way and Highway 213 began.
Friday,
March 5, 2004 - ODOT surveyors were on the farm to drive stakes to
outline the proposed right-of-way requirements for the project. The
area directly in front of the house and gardens has been minimized as much
as possible and still accomplish the road widening but the impact to the
field seems to a bit drastic. I will call and talk to Rick this next
week.
Rick explained that they have to install the wide
safe ditches and this is why the amount of property being taken is so
great.
Wednesday, January 11, 2003 - Well the
project is underway. Sometime last week the utility companies began
the initial stages in preparation for relocating power poles and lines,
gas pipes, etc. I received an email from the ODOT project manager
today saying that he just heard that the contractor was planning on
beginning the project at the end of this month instead of the end of
March. Yikes! The plants that I want to rescue and move in the
path of destruction are barely dormant. It is time to get busy!!!
Saturday, July 30, 2004 - This is just a
"catch-up" entry. The appraisal seemed unbiased and pretty fair. It
is a done deal. Paperwork is sign, the project design is complete
with all of our compromises and negotiations, and it should go out for bid
in August and scheduled to start in the spring. This will give us
time to relocate some plants and move a field fence.
In a nutshell, the original design from a decade
ago would have cost us a couple of acres and forced us to relocate out
house on the property. It would have also caused the loss of several
very old trees. The final design required a little over a half acre
and if all goes well, the trees will be spared by using curbs, culverts
and guard rails instead of huge, wide, open ditches. This design
also required less land.
We hope to be able to afford the cost of erecting
a concrete wall along the property line separating the highway from our
front yard. Along with the physical barrier, we are hopeful that it
will deflect some of the noise.
If I was asked to make a recommendation to anyone
dealing with a road project like this, I would highly suggest that you get
to know everyone involved. Keeping an open mind is also helpful.
Realize that a public project will generally occur whether you want it too
or not. Establishing personal relationships with the folks that plan
the project, design it, determine your compensation, etc., is highly
beneficial. They are people too and understand that their
decisions not only benefit all of the citizenry in the area, but impact
your life as well. They have a job to do and from every one I met,
they felt a sense of responsibility to their employers - the citizens of
Oregon.
Monday, April 12, 2004 -
A property appraiser, hired by ODOT, was out today to begin working on
setting a value on the land, fences, and landscaping that they will be
removing.
Coincidentally, commencement of the demolition of
the two houses on the corner of Liberal Way and Highway 213 began.
Friday,
March 5, 2004 - ODOT surveyors were on the farm to drive stakes to
outline the proposed right-of-way requirements for the project. The
area directly in front of the house and gardens has been minimized as much
as possible and still accomplish the road widening but the impact to the
field seems to a bit drastic. I will call and talk to Rick this next
week.
Rick explained that they have to install the wide
safe ditches and this is why the amount of property being taken is so
great.
Tuesday, January 13, 2004
- I arrived at the office to a voice mail from Rick Keene, not in
reference to my question about the increase in the amount of right-of-way
being taken, but bringing up the issue of driveways into the properties
from the road. This issue of highway access was suppose to have been
finalized with our agreed to compromise as outlined on
May 20, 2003. With the receipt of the right-of-way acquisition
drawing, ODOT's side of the compromise appears to be reneged on.
In discussing the issue with him, he went back to
the designer and they were able to use a guard rail all the way from the
south driveway to the north driveway and thus reduce the amount of land
required in front of the house and farmyard.
Thursday, January 8, 2004
- Received a call from the local Molalla CPO representative. He said
that he was meeting with Rick Keene to address some of the design issues
that he presented in a letter. It sounded like most had to do with
the corner properties on Liberal Way. He is interested in having
them maintain the mature trees and plant with native plants to provide
wildlife habitat.
Friday, December 24, 2003 - Received a letter from Darlene Rose, the right-of-way representative. It contained a map of physical area
that ODOT is planning on acquiring from us for the project. It seems
that I did in fact understand the drawings that were sent to me in August. It looks
like an old map and the land they are planning on acquiring looks like the
old plan. I called and talked to Rick Keene and he said that he
would make some calls and let me know what was going on.
Wednesday, August
6, 2003
- Rick
Keene called and was a bit upset with me. Before sending me the
drawing he had warned me that there were lines on there that I might not
understand and that he wanted to go over it with me in person. The
drawing is still very preliminary (the drainage portion is not even
designed) and several features like a curb and guard rail, were actually
on the drawing.
I apologized for
jumping the gun by sending out the email without waiting instead for our
meeting. He accepted my apology and said, "we'll try our best
to minimize the project effects to the farm and house."
Tootie Smith's Chief
of Staff emailed thanking me for keeping them in the loop.
Tuesday, August
5, 2003
- I
emailed Rick Keene (copying Darlene Rose, who was at the May 20th meeting)
as well as State
Representative, Tootie Smith's office.
I said:
|
"I received
the drawing that you mailed this past Friday and am really disappointed.
The first thing that I noticed is that its date (5/7/03) predates our
last meeting on May 20th. This drawing was never shown to us at that
time. Our May 20th
meeting was called because you wanted to go over a proposal for
integrating two of our highway access points (driveways) into one and to
document features that we wanted incorporated into the design. As we
discussed, the following list of design features would help to alleviate
the need of having ODOT move our house further back into the property.
- Minimize the
setback (mainly with the use of storm drains / culverts and curbs).
- Modify the
design to preserve the ancient oak tree.
- Install guard
rails for safety. (Rick's idea, not my requirement)
- Install
visual/noise barrier (concrete wall like along other ODOT projects)
from driveway to driveway.
- Replace fences,
gates, and landscaping.
As your were
leaving, I asked you how long it would be before we heard back with a
decision on the above list. You said, "Right now. If this is what
you want, this is what we'll do".
On the new drawing
that I received, the driveway reconfiguration is shown but I only agreed
to this contingent on the other points above. Not one of these
modifications was illustrated. As a matter of fact, this drawing shows a
much greater impact than the drawings that you brought out for the
walk-through on May 20th. It looks strikingly like the original design
dating back to the early 90s where our existing culverts are removed and
huge, wide, car friendly (property owner unfriendly) ditches are
proposed.
I feel like we are
back to the beginning and that our safety, property rights, and
ultimately our well being, are not being considered. At least they are
not being documented in the project drawings presented.
I am truly hoping
that the wrong drawing was sent and that you will have something more
representative of our past several months worth of discussion in your
possession for our meeting this Thursday."
|
Saturday, August
2, 2003
- Received
the drawing that Rick sent on Friday, August 1. It was so upsetting
that I withheld contacting ODOT (Rick Keene) about it until I had time to
calm down a bit.
Tuesday, July 29, 2003
- I
emailed Rick back stating that a Thursday meeting was fine but to please
go ahead and send me out the latest drawing in the mean time.
Tuesday, July 29, 2003
- Received
a voice message from Rick Keene stating that he had received my email and
that the latest design was "difficult to read" that I "may
or may not be able to decipher", and that he would prefer to meet
with me again in person to go over it. He said that he wanted to
meet here with the actual designer to go over it.
Monday, July 21, 2003
- Another
month had passed so I emailed Rick Keene asking what the outcome of the
meeting had been.
Thursday, June 19, 2003
- Rick
emailed back stating that he had a, " . . . team meeting scheduled
next week. I haven't seen the latest drawings but the designer was
instructed to include the provisions you and I discussed. I'll pass it on
to you after the meeting." He concluded the email with, "
I appreciate you e-mailing me asking for updates. I'll make it a point to
keep you in the loop. Take care."
Wednesday, June
18, 2003
- Emailed
Rick Keene asking if he could send me a new drawing showing the design
modifications that we agreed upon at our meeting a month prior. I
also asked to be kept in the loop about the project status.
Friday,
July 11, 2003 - I was not able to attend the June 16th Planning
Commission Meeting but did receive a status update from Kay Pollack of the
County Planning Division.
She
said, "The Commission continued the Green Corridors hearing until
November 17th, with a work session scheduled on September 22. They asked
staff to come back with a more definitive interpretation of the County's
requirement to Metro to comply with the Green Corridors provisions, as
well as refinement of the identified problems. Generally the Commission
expressed concern that if there are gaps in the existing ordinance
provisions, and if different review procedures and criteria are needed,
then they should address the entire rural area, not merely two highway
corridors. They asked staff to prepare a suggested process for doing that.
A
subcommittee of the Planning Commission has been appointed (Comm. Johnson,
Comm. Pearson, and Comm. Andreen) to work with staff in refining the
charge and preparing a proposal to accomplish that charge."
Tuesday,
May 20, 2003
- I still
have not heard back from the ODOT advocate but I assume that it is because
of the scheduled meeting today. I did get a call from State
Representative, Tootie Smith's office Chief of Staff. She
said that she had talked to the advocate yesterday and that she was told
that they had "four plans" to present to me and that she would
be contacting me. Although I did not hear from her, I assume that
she meant that they had solutions to my four main concerns.
Rick
Keene, Project Planner, and Darlene Rose, Senior Right of Way Agent,
arrived at about 10:30 A.M. to go over our concerns and to present some
ideas and alternatives.
Right
up front he said that the plan to cut the grade of the road to increase
the safe travel speed has been dropped. That was very
unexpected. Logically, since this area is a 45 M.P.H. speed zone, it
just did not make sense to "speed the road up" by lowering the
grade. It would have meant that people would be speeding past the
house at 75 and 85 M.P.H. instead of 55 and 65 M.P.H.
He then
discussed the ODOT position that access
points onto the Highway 213 corridor are serious concerns and need to be
limited. Since our properties have four access points (driveways) onto the highway, they are trying to limit them. They
agreed to replace the southern driveway onto the separate tax parcel but
wanted to present an alternative solution to existing farm and house driveways.
Basically
they want to merge the use of our southern farm entry point with the house
driveway and removing the existing house driveway. I said that this
would be a compromise I would accept if we were able to preserve at least
the oak tree that is hundreds of years old and implement the other design
features that will:
-
Minimize the setback (mainly
with the use of storm drains /
culverts and curbs instead of ditches).
-
Modify
the design to preserve the ancient oak tree.
-
Install guard rails for safety.
(This was Rick's idea not mine)
-
Install
visual/noise barrier (concrete wall) from driveway to driveway.
-
Replace
fences, gates, and landscaping.
This would keep us from having
to take the alternative course of action which was to fight to move our
house further back into the property.
As
he was leaving, I
asked Rick how long it would be before we heard back with a decision. He
said, "right now. If this is what you want, this is what we'll
do".
He said that it will be about two months before they hear
approval of the overall plan based on the perceived impact to the view of
the "historic" barn on Stipp's old place. They have
purchased one house across the street next to the church and are
proceeding with the purchase of the one on the corner. Both will be
removed soon.
From
my interactions and conversations over the years and months with both Rick
and Darlene, my heart really likes them and I believe that they are
working hard for a compromise that meets the safety and design goals of
the state while
maintaining the livability and safety of our farm, home and
business. My head trusts and prays that what has been promised will
be done and that I am not bring naive.
I
will update the ODOT advocate regarding
what Rick presented and promised today.
Monday,
May 19, 2003 -
I attended the "Planning Commission Public Hearing to consider the
Planning Commission's recommendations on the proposed Comprehensive Plan
and Zoning Development Ordinance amendments (File ZDO-197) to create and
implement a Green Corridor Design Plan for areas bordering segments of
Highways 99E and 213". The county staff members presented their
proposal (click
here for zoning changes)
to the planning commissioners. They asked staff a few questions and
then the various CPOs had the opportunity to speak.
Mulino
CPO's representative made a statement, as I expected, basically saying
that the proposed 1000 foot from the highway centerline (2000 total)
setback was excessive and that 500 feet total was better. Not that
the plan was unnecessary. He then made a presentation of additional
restrictions he wanted included in the proposed zoning changes pertaining
to lighting. Specifically the wattage and direction of
lighting. This was very specific, and part of his personal
involvement with the "Dark Skies Initiative"
(additional
links here)
and that bright lights are disruptive to his night driving as he has a detached
retina.
Carus
CPO expressed opposition to the proposal. The speaker was a
multi-generation farm resident.
Molalla
CPO's Dick Miller made a statement in opposition but then made comments
similar to Mulino's regarding the width of the affected area and then
presented information about how cell towers should be painted and
otherwise camouflaged to look like fir trees.
With
the CPO testimony concluded, the chairperson asked from public testimony
in favor of the proposal. No one was there in favor and the audience
laughed loudly. She asked for testimony in opposition and was met
with multitudes of hands.
As the evening of testimony progressed, several common themes emerged.
-
The
property owners potentially affected by this proposal were never
surveyed nor properly represented.
-
The
county should not enter into Intergovernmental Agreements (IGAs) with
the cities of Oregon City, Molalla and Canby as they have no jurisdiction
nor authority over these areas and should have no say in issues that
affect the rights of these property owners.
-
Nor
does Metro have any rights to dictate and impose additional zoning
restrictions.
-
Current
zoning and land use regulations are doing the job at meeting all of
the "Green Corridors" goals. The question was raised
as to why try and fix something that isn't broke.
-
Property
ownership in America is a foundational principle. This should
not be further restricted beyond what it already is.
Testimony
continued until 11:00 P.M. when the planning commissioners agreed that
there were too many issues to resolve and that the process was too
rushed. A motion was made to leave the public record open 5:30 P.M.
on Monday, June 16th and adjourn again at 6:30 P.M. on that date for
further discussion and vote. I hope and pray that democracy is
proven to work, that common sense and logic prevail, and that this stopped
before going any further.
If it passes, it moves up the the Board of County Commissioners on
Wednesday, June 18th at 9:30 A.M.
The fundamental concept is sound. I hope that our farm will remain a
viable agricultural property for generations to come. It is already
zoned for exclusive farm use. The "Green Corridor" would simply
force a facade along the highway. Much like driving along a highway
and marveling at the beauty of the forest that you are driving through
only to realize that the land is clear-cut just inside a certain boundary
line.
It does nothing to actually protect farmland from development nor protect
it permanently. The "Green Corridor" is only valid until the urban
growth boundaries of the Portland Metro Area and Canby or Molalla gobble
up the surrounding land. All of the other issues are addressed in
rules and zoning code already on the books. If these were enforced,
on a county wide basis, not just along the main highways of 99E and 213,
the county would be a much more beautiful place.
Friday,
May 16, 2003 -
The Senior Right of Way Agent called and asked if she could come out to
see the property. We had met her at the March public
meeting and had invited her out. I told her that Rick was coming
out, possibly Tuesday, and that she should contact him and perhaps share a
ride.
Thursday,
May 15, 2003
- I
received an email from Rick Keene, the Project Team Leader, in response to
my email requesting an update to the plan. I specifically asked to
see several items updated on the plan drawing. The main points were
to restore the field access driveway for the southeast parcel, restore our
south farm entrance driveway, use a culvert and curb system for drainage
instead of the wide, high impact "safety ditch" design,
protection of the old trees - especially the old oak tree, implementation
of safety, visual, and noise suppression features. He replied today
asking if we could get together onsite to discuss some ideas and compromises
but said that the upper driveway was not "permitted", that is,
there was no permit granted in the past, so it would net be restored.
I
replied to the email stating that the driveway was there in the 30s when
my Grandparents purchased the property, it was there in the 80s, when I
purchased the property, and it is the only access point to that parcel
which is a separate tax lot.
Thursday,
May 15, 2003
- Mulino, Molalla, and Carus CPOs
(Citizen Planning Organizations) combined meeting to discuss the
"Green Corridor" project. I was very disappointed in the
fatalistic attitudes of the CPO "board" members. They
statement was made that "this plan is going to happen anyway, we just
want to work with them to make it as palatable as possible".
This
is simply wrong! The government still works for us and should be
doing the job that we want them to. They are not supposed to invent
things to do, create new areas of responsibility for no reason and
certainly not work on plans and processes that create confusion,
redundancies, and trampling on the rights of citizens who own
property. This "Green Corridor" study does all of these
things.
I
left the meeting angry, sad, and disappointed. The CPOs are supposed
to exist as a representative body made up of local property owners.
What I witnessed was a tiny handful of people, many of whom have very
specific personal interests, controlling the opinion presented to the
county planning commission.
The
people presently active in the CPOs are not completely to blame. I,
for example, will be more diligent in my involvement in future sessions
and be sure to make my voice heard. Citizens, especially in Oregon
it seems, cannot sit back and take it for granted that the government will
take care of things and do what is right. Nor should they hold the
attitudes that they are powerless in the process. We are
the government and if they do not hear from us, they hear from the
minority of special interest groups that have very specific agendas which
are often counter to logic, personal freedom or economic reason.
Wednesday,
May 14, 2003
- I emailed State
Representative, Tootie Smith's office Chief of Staff to ask if she had
heard any news and to tell her the latest with ODOTs advocate as well as
that I emailed the project planner asking for a status update.
Tuesday,
May 13, 2003 - The ODOT advocate emailed and said that she had
received information, will be reviewing it, and attempt to get back to me
this week.
Friday,
May 9, 2003 - I emailed the ODOT advocate asking for an update.
Tuesday,
May 7, 2003
- Received a letter requesting that we sign a
"Right-Of-Entry" authorization for the ODOT archeologist
visually inspect the area proposed to be impacted by the highway project.
Wednesday, April
16, 2003
- The person from ODOT, an advocate, emailed to tell me that
she had received information from State
Representative, Tootie Smith's office Chief of Staff and would discuss
the issues with the design team.
Tuesday, April 15, 2003
- I emailed State
Representative, Tootie Smith's office Chief of Staff to confirm receipt
of the voicemail messages and to thank her for keeping the ball rolling.
Monday,
April 14, 2003 - State
Representative, Tootie Smith's office Chief of Staff called (I was out in
the field and missed the call). She left messages that stated that
she was in contact with a person from ODOT about our safety concerns and
desire to have the house relocated. She forwarded the person our
original email and they are supposed to contact me within the next couple
of days.
Thursday,
April 10, 2003 - Attended the public open house that the county was
holding. The "Green
Corridor"
project was being presented as a done deal. The county rep was using
terminology implying that the property owners wanted these additional
zoning restrictions placed on their land. I do not have a lot of
first hand, personal experience dealing with government workers any more,
but it amazed me how condescending they treated me and when drawn into a
sound, logical debate on the issues, how quick they were to get out of the
area - literally, stop listening and left the room! Ignorant and asinine come to mind as proper adjectives.
Click
here for the project history.
I
did meet a couple of other land owners there that are vehemently opposed
to this "Proposed adoption of ZDO-197. Comprehensive Plan and
Zoning and Development Ordinance amendment to create and implement a Green
Corridor Design Plan for areas bordering segments of Highways 99E and
213."
The
county rep kept using terms implying that this is something that
"we" wanted. I asked him to define. After a few
rounds of side-stepping and double-talk, I asked him a specific question
about "who" is driving this effort and "who" is paying
for all of the resources (print, posters, postage, labor, etc.). He
answered that it is from a "Metro"
grant. [Metro is a super-governmental organization with power just under
the state and over the county and local governments in a tri-county region
of Oregon. And you thought your area had too much
government!]. So, basically, what he said is that "we"
(actually people in a small, powerful, special interest population in the
city) want to ensure that their (rare) weekend excursions into the country
are "protected" but without any impact on their lives and all of
the impact on the rural landowners. Sweet deal.
Thursday, March
27, 2003
- State
Representative, Tootie Smith's office Chief of Staff left a message
stating that she was still researching but my voicemail box filled up an d
I missed part of the message.
Tuesday, March 25, 2003
-
Had a nice conversation with State
Representative, Tootie Smith's office Chief of Staff. I explained
our concerns, our historical background, and our connection to the
community. She is going to speak with State
Representative, Tootie Smith's office tomorrow and see what course of
action to take. She said that she would call back Thursday
afternoon.
Wednesday, March
12, 2003
- Resent the email per Dianne's phone request
Tuesday, March 11, 2003
-
Received a phone message from State
Representative, Tootie Smith's office Chief of Staff, Dianne. She said that
she had been on personal leave and that she had received Denise's message
from February 28th. She said that she did not see the email that I
sent on February 22nd and assumed that one of the legislative assistants
had already replied to us. (This is not the case). She said that we
could try calling again or since she is now back in the office, email her
again. As soon as I get today's orders out, I will write another
email outlining the issues, the concerns, and what we would like to see
happen.
Wednesday,
March 5, 2003
- Received a call from a customer offering support and
saying that they had a similar event happen to them. They were able
to avert having the old trees in front of their place from being removed for a road
widening project but that it was a long fight.
Tuesday, March 4, 2003
-
No contact from State
Representative, Tootie Smith's office office. Met with the
ODOT project
leader at 3:00 this afternoon at our house. He brought the drawings
that were to scale and with more detail. It illustrated that the
road is drastically changing in front of our house. It is almost incomprehensible and
hard to imagine. The road is currently level with our
property. They will be lowering the grade of the road by about 3
feet. At the same time they will be widening the road to the current
right-of-way and beyond. All of the ancient trees will be removed
and the house will be exposed to very dangerous highway traffic. We are
praying that it works out to be feasible to move our house to a safer set
back distance.
The
public meeting was at 5:30 this afternoon and we got a chance to meet with
the senior right of way manager for the project. It was her first
day on the job as here boss unexpectedly took early retirement. We were able to get to
know her and she us. We were able to describe our history in the
area, our commitment to the community, and our concerns. We invited
her out to see the place some sunny day.
Everyone
we have met seems to be very nice and I believe that it is good that they
can meet the people that the plans are affecting. At the same time
it is beneficial for us to meet and get to know them so that they are not
simply faceless bureaucrats.
Monday,
March 3, 2003 - Nothing to report. No call from State
Representative, Tootie Smith's office office.
Friday,
February 28, 2003
-
Received an email from the project manager. He suggested coming out
with better drawings so that he could explain the current design on site.
It is hard to wait but it has been hanging over all of our plans for 10
years. Another couple of days of uncertainty will have to do.
Denise called State
Representative, Tootie Smith's office but was told
by the person that answered the phone that the assistant we needed to talk
to was out and that they would call Monday.
Thursday,
February 27, 2003 - We still have not receive any acknowledgement of my email
from State
Representative, Tootie Smith or her office. Denise called
but got voicemail so she left a message. I have received a couple of
referrals to legal firms specializing in land use and eminent domain
issues.
The manager sent
me a sketch of the project drawing.
Click
here to see it. I shaded the part of the drawing
representing our farm. I emailed Mr. Keene to ask for better
drawings.
Monday,
February 24, 2003
- I did not receive any acknowledgement of my email
from State
Representative, Tootie Smith or her office today. Although
we work all weekend, Monday's are still one of our busiest days of the
week. Answering correspondence, filling and shipping orders, etc.
take priority so tomorrow Denise will call and I will send a registered
letter. We won't know a lot until we see a copy of the plan.
The public meeting is scheduled for Tuesday, March 4, 2003, 5:30 to 7:30
p.m. at the Molalla Fire Department.
Saturday,
February 22, 2003 - Life is never dull or boring here on the
farm. Even though I rarely get off of the farm except for on Sunday,
the internet connection and phone provide me with the ability to talk with
friends, family and customers, all over the world, on a daily basis.
It is amazing the number of relatives I have "met" over the
years as well as the friendships established.
History
is alive here on the farm. It is so entwined with my daily life that
it is hard to explain without going into a long dissertation. In a
nutshell, working the same ground and living in the same house of my
ancestors is awesome. It is never taken for granted.
A
New / Old Battle
Unfortunately,
the farm is not an island and the present converges on and impacts the
past. I was informed on Friday (2/21/03) that the Oregon Department
of Transportation (ODOT) is on a fast track to reopen a project that was
shelved back in 1992. They intend to widen and re-grade the highway
in front of the house to a point where we would lose nearly all of our
front yard (including the all of the old trees) bringing the highway and
ditches within feet of our front door.
Without
understanding the traffic load that this highway supports, it is hard for
people to grasp the severity of the issue. Highway 213 is a major
state highway that feeds this part of the county. Thousands
of vehicles pass in front of my house daily. Much of this traffic
includes
large vehicles supporting the industries out here (tractor-trailers, log
trucks, dump trucks, propane carriers, fuel tankers, etc.).
If
this plan is implemented as ODOT intends, there will be nothing to prevent
some sleepy truck driver or drunk driver from plowing into our
house. It would be only a matter of time. As it is now, deep
ditches and large trees have saved us! Can you imagine going to bed
every night having to wonder if tonight was the night that you get slammed
into? I cannot. Additionally, we have concerns regarding the
impact the traffic will have on the integrity of our old wood framed house
when roaring past at such a close distance.
I
have emailed my State
Representative, Tootie Smith, asking for her to get involved in
the project so that we are not run over by "progress".
Progress
and growth are inevitable as our society expands. This project is
one that the business owners of Molalla have been lobbying. Although I am a
sentimental person and value the past, I am a realist and live in the
present. However, I strongly believe that if I am being impacted for
the good of many, the burden should not be mine to bear alone.